| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| General Contractor Services for Stormwater Facility MD1745 Retrofit | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Removal, hauling, and disposal of accumulated sediment, vegetation, and earthwork | 4200 | cubic yard | $50.00 | $210,000.00 | Construction |
| Installation of sediment forebay | 1 | each | $30,000.00 | $30,000.00 | Construction |
| Installation of plunge pool at existing inflows | 1 | each | $20,000.00 | $20,000.00 | Construction |
| Installation of deep plunge pool at existing inflows | 1 | each | $25,000.00 | $25,000.00 | Construction |
| Construction of wetland cells with intercell berms | 3 | each | $75,000.00 | $225,000.00 | Construction |
| Construction of flow channel through wetland cells | 1 | lot | $40,000.00 | $40,000.00 | Construction |
| Installation of landscape plantings | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Project Management and Oversight (General Contractor) | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Estimated Bid Value | $750,000.00 | ||||