| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Removal of existing H.B. Smith Series 28A-8 CRN# D-605 Boiler #2 | 1 | each | $5,000.00 | $5,000.00 | Construction |
| Lochinvar M# CHN2072-M13 Copper-fin gas boiler | 1 | each | $40,000.00 | $40,000.00 | Facilities |
| Installation of new Lochinvar M# CHN2072-M13 Copper-fin gas boiler | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Reconnect existing flue gas piping to new boiler | 1 | lot | $3,000.00 | $3,000.00 | Construction |
| Wire electrical to the new boiler | 1 | lot | $4,000.00 | $4,000.00 | Construction |
| Replace existing pipe insulation | 1 | lot | $2,000.00 | $2,000.00 | Construction |
| Startup of pump and boiler | 1 | each | $2,500.00 | $2,500.00 | Facilities |
| Staff training on new boiler system | 1 | lot | $1,500.00 | $1,500.00 | Professional Services |
| Proper disposal of all project related waste | 1 | lot | $3,000.00 | $3,000.00 | Facilities |
| Annual system inspection, testing, and repairs for new boiler | 1 | year | $19,000.00 | $19,000.00 | Facilities |
| Estimated Bid Value | $110,000.00 | ||||