| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Mobilization and Demobilization | 1 | lot | $92,500.00 | $92,500.00 | Construction |
| Construction Layout | 1 | lot | $92,500.00 | $92,500.00 | Construction |
| Quality Control | 1 | lot | $55,500.00 | $55,500.00 | Construction |
| Site Preparation | 1 | lot | $185,000.00 | $185,000.00 | Construction |
| Gravel Access Road - AASHTO #1 | 285 | TON | $40.00 | $11,400.00 | Construction |
| Gravel Access Road - 1 1/2" Crusher Run | 315 | TON | $35.00 | $11,025.00 | Construction |
| Haul Road - AASHTO #1 | 860 | TON | $40.00 | $34,400.00 | Construction |
| Haul Road - 1-1/2" Crusher Run | 375 | TON | $35.00 | $13,125.00 | Construction |
| Existing Tomes Driveway Rehabilitation - AASHTO #1 | 15 | TON | $45.00 | $675.00 | Construction |
| Existing Tomes Driveway Rehabilitation - 1 1/2" Crusher Run | 240 | TON | $40.00 | $9,600.00 | Construction |
| Gould Farm Rd CR 23/3 Rehabilitation - AASHTO #1 | 60 | TON | $45.00 | $2,700.00 | Construction |
| Gould Farm Rd CR 23/3 Rehabilitation - Class 1 Aggregate | 415 | TON | $40.00 | $16,600.00 | Construction |
| Ditch Cleanout | 1000 | LF | $5.00 | $5,000.00 | Construction |
| Temporary Fence | 1738 | LF | $3.00 | $5,214.00 | Construction |
| Livestock Fence | 6737 | LF | $8.00 | $53,896.00 | Construction |
| Farm Gate | 5 | EA | $300.00 | $1,500.00 | Construction |
| Stabilized Construction Entrances - AASHTO #1 | 100 | TON | $50.00 | $5,000.00 | Construction |
| Safety Fence | 893 | LF | $4.00 | $3,572.00 | Construction |
| Rock Check Dam | 7 | EA | $750.00 | $5,250.00 | Construction |
| Bonded Fiber Matrix | 30190 | SY | $0.75 | $22,642.50 | Construction |
| Woven Belted Silt Fence | 3282 | LF | $4.00 | $13,128.00 | Construction |
| Sediment Basin | 1 | EA | $10,000.00 | $10,000.00 | Construction |
| Riprap Apron Outlet Protection | 2 | EA | $2,500.00 | $5,000.00 | Construction |
| Temporary Diversion Channel | 435 | LF | $15.00 | $6,525.00 | Construction |
| Pump Around With Dewatering Bag | 1 | EA | $7,500.00 | $7,500.00 | Construction |
| Revegetation | 18.03 | ACRE | $3,000.00 | $54,090.00 | Construction |
| Type V Riprap Channel | 1939 | LF | $150.00 | $290,850.00 | Construction |
| Channel Energy Dissipator | 1 | EA | $15,000.00 | $15,000.00 | Construction |
| Unclassified Excavation | 58758 | CY | $15.00 | $881,370.00 | Construction |
| Estimated Bid Value | $1,850,000.00 | ||||