| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Tree clearing and stump removal | 1 | lot | $250,000.00 | $250,000.00 | Construction |
| Installation of erosion and sediment control measures | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Mass grading | 1 | lot | $750,000.00 | $750,000.00 | Construction |
| Water main extension by jack and bore methods | 1 | lot | $500,000.00 | $500,000.00 | Construction |
| Construction of a lift station with associated appurtenances | 1 | each | $800,000.00 | $800,000.00 | Construction |
| Electrical service installation for lift station | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Standby generator installation for lift station | 1 | each | $100,000.00 | $100,000.00 | Construction |
| Construction of a force main including jack and bore crossings | 1 | lot | $550,000.00 | $550,000.00 | Construction |
| Estimated Bid Value | $3,250,000.00 | ||||