| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Removal and replacement of main plumbing lines throughout facility | 1 | lot | $350,000.00 | $350,000.00 | Construction |
| Demolition and reconstruction of selected CMU walls | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Demolition and replacement of selected doors and frames | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Demolition of gypsum board ceiling and associated light fixtures within housing units | 1 | lot | $80,000.00 | $80,000.00 | Construction |
| Installation of new gypsum board ceiling within housing units | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Installation of new light fixtures within housing units | 1 | lot | $60,000.00 | $60,000.00 | Construction |
| Demolition of CMU walls, doors, and frames for shower hub development | 1 | lot | $90,000.00 | $90,000.00 | Construction |
| Construction of new CMU walls, doors, and frames for shower hub layout | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Installation of new light fixtures in shower hubs | 1 | lot | $40,000.00 | $40,000.00 | Construction |
| General project management and supervision for renovation | 1 | lot | $100,000.00 | $100,000.00 | Professional Services |
| Estimated Bid Value | $1,250,000.00 | ||||