| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Sanitary Sewer Main Replacement (8" HDPE, pipe burst method) | 848 | LF | $120.00 | $101,760.00 | Construction |
| Sewer Lateral Replacement | 1 | lot | $40,000.00 | $40,000.00 | Construction |
| Manhole Rehabilitation | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Water Main Installation (6" C-900 PVC) | 530 | LF | $80.00 | $42,400.00 | Construction |
| Water System Connections to Existing System | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Longside Water Laterals | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Shortside Water Laterals | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Rollover Curb and Gutter Installation (24") | 945 | LF | $45.00 | $42,525.00 | Construction |
| Storm Pipe Installation (18") | 560 | LF | $60.00 | $33,600.00 | Construction |
| Storm Pipe Installation (15") | 30 | LF | $50.00 | $1,500.00 | Construction |
| Curb Inlets | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Grate Inlets | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Roadway Pavement Overlay | 1 | lot | $250,000.00 | $250,000.00 | Construction |
| Sediment Control | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Grassing | 1 | lot | $8,000.00 | $8,000.00 | Construction |
| Project Management and Supervision (120 calendar days) | 120 | day | $500.00 | $60,000.00 | Professional Services |
| Estimated Bid Value | $750,000.00 | ||||