| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Boiler System Replacement (including new boilers, pumps, piping, controls) | 1 | lot | $750,000.00 | $750,000.00 | Construction |
| Hot Water System Replacement (including new water heaters, storage tanks, circulation pumps) | 1 | lot | $300,000.00 | $300,000.00 | Construction |
| Demolition and Removal of Existing Boiler and Hot Water Systems | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Electrical Upgrades and Connections for New Systems | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Plumbing and Gas Line Modifications/Connections | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Project Management and Engineering Services | 1 | lot | $25,000.00 | $25,000.00 | Professional Services |
| Estimated Bid Value | $1,250,000.00 | ||||