| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Preliminary Engineering Report (PER) preparation (NCDEQ SRF format) | 1 | project | $75,000.00 | $75,000.00 | Professional Services |
| Application for Finding of No Significant Impact (FONSI) | 1 | project | $25,000.00 | $25,000.00 | Professional Services |
| Design services for potable water interconnect (35,000 LF of 12" water transmission lines and appurtenances) | 1 | project | $500,000.00 | $500,000.00 | Professional Services |
| Bidding services for potable water interconnect construction | 1 | project | $100,000.00 | $100,000.00 | Professional Services |
| Construction oversight services for potable water interconnect (35,000 LF of 12" water transmission lines and appurtenances) | 1 | project | $700,000.00 | $700,000.00 | Professional Services |
| Estimated Bid Value | $1,400,000.00 | ||||
Sign up free to see the agency name and the original bid posting link. Pro adds the 1 document, contracting-officer contacts and AI response outlines.