| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Structural stabilization of tunnel entrance and exits | 1 | lot | $750,000.00 | $750,000.00 | Construction |
| Disposal and removal of existing supports | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Masonry repairs | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Installation of Instrumentation & monitoring equipment | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Replacement of existing air lock doors at entrance and exits | 2 | each | $50,000.00 | $100,000.00 | Construction |
| Replacement of existing security doors at entrance and exits | 2 | each | $25,000.00 | $50,000.00 | Construction |
| Replacement of existing suspended ceiling system, components, and associated ductwork | 1 | lot | $300,000.00 | $300,000.00 | Construction |
| Replacement of existing bypass tunnel door | 1 | each | $20,000.00 | $20,000.00 | Construction |
| Replacement of existing lighting and distribution system components | 1 | lot | $400,000.00 | $400,000.00 | Construction |
| Replacement of existing safety handrails | 1 | lot | $180,000.00 | $180,000.00 | Construction |
| Replacement of the existing mine phone system and components | 1 | lot | $80,000.00 | $80,000.00 | Telecommunications |
| Labor, equipment, supplies, testing & inspections, and incidentals (overall project management and execution) | 1 | lot | $670,000.00 | $670,000.00 | Construction |
| Estimated Bid Value | $3,000,000.00 | ||||