| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Preparation of Stage 3 Closure Area to subgrade | 1 | lot | $500,000.00 | $500,000.00 | Construction |
| Construction of geosynthetic landfill capping system | 7 | acre | $350,000.00 | $2,450,000.00 | Construction |
| Preparation of barrier protection and topsoil layers | 1 | lot | $300,000.00 | $300,000.00 | Construction |
| Installation of surface water drainage | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Miscellaneous work related to Stage 3 Closure Construction | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Estimated Bid Value | $3,500,000.00 | ||||