| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Channel Cleanout of Belle Fountain Ditch region (Bypass of Steele and Main Ditch) | 1 | lot | $1,200,000.00 | $1,200,000.00 | Construction |
| Furnishing all plant (equipment) for channel cleanout | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Furnishing all labor for channel cleanout | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Furnishing all materials for channel cleanout | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Incidental related work (project management, site preparation, cleanup, etc.) | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Estimated Bid Value | $1,500,000.00 | ||||