| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Project Management and Engineering Services for Water Tank Rehabilitation | 1 | lot | $150,000.00 | $150,000.00 | Professional Services |
| Site Preparation and Mobilization for Water Tank Rehabilitation | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Water Storage Tank Cleaning and Disinfection (Half Million-Gallon) | 1 | each | $75,000.00 | $75,000.00 | Construction |
| Interior Coating Removal and Surface Preparation (Half Million-Gallon Tank) | 1 | lot | $120,000.00 | $120,000.00 | Construction |
| Application of New Interior Coating System (Half Million-Gallon Tank) | 1 | lot | $180,000.00 | $180,000.00 | Construction |
| Exterior Coating Removal and Surface Preparation (Half Million-Gallon Tank) | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Application of New Exterior Coating System (Half Million-Gallon Tank) | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Structural Repairs and Welding for Water Storage Tank | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Installation/Replacement of Tank Accessories (Ladders, Vents, Hatches, etc.) | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Final Inspection, Testing, and Commissioning of Rehabilitated Water Tank | 1 | lot | $50,000.00 | $50,000.00 | Professional Services |
| Demobilization and Site Restoration | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Estimated Bid Value | $1,250,000.00 | ||||