| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Design-Build Services for Temporary Chiller Installation | 1 | lot | $3,500,000.00 | $3,500,000.00 | Construction |
| Professional Design Services (Architectural, Engineering) | 1 | lot | $700,000.00 | $700,000.00 | Professional Services |
| Construction/Installation of Two Government-Furnished Trane 1250-ton Chillers | 2 | each | $800,000.00 | $1,600,000.00 | Construction |
| Integration of Chillers into Central Chilled-Water System | 1 | lot | $300,000.00 | $300,000.00 | Construction |
| Design and Construction/Installation of Weatherproof Chiller Enclosures | 2 | each | $250,000.00 | $500,000.00 | Construction |
| Design and Construction/Installation of Associated Mechanical Infrastructure | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Design and Construction/Installation of Associated Electrical Infrastructure | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Civil Site Preparation and Improvements | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Architectural Improvements (New and Existing Buildings/Enclosures) | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Commissioning Services for Chiller System | 1 | lot | $100,000.00 | $100,000.00 | Professional Services |
| Estimated Bid Value | $3,500,000.00 | ||||
Sign up free to see the agency name and the original bid posting link, plus the 1 document, contracting-officer contacts and AI response outlines. Every feature is free through December 31, 2026.