| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Coordination and delivery of YRBM-50 vessel to contractor facility | 1 | lot | $15,000.00 | $15,000.00 | Transportation |
| Vessel wash and cleaning upon docking | 1 | lot | $10,000.00 | $10,000.00 | Facilities |
| Required inspections (general vessel condition) | 1 | lot | $25,000.00 | $25,000.00 | Professional Services |
| Fender repairs | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Removal of existing zinc anodes | 1 | lot | $5,000.00 | $5,000.00 | Facilities |
| Installation of new zinc anodes | 1 | lot | $10,000.00 | $10,000.00 | Facilities |
| Ultrasonic measurement of hull, freeboard, and exterior decks plating thickness | 1 | lot | $20,000.00 | $20,000.00 | Professional Services |
| Repair of hull, freeboard, and exterior decks areas below minimum thickness | 1 | lot | $250,000.00 | $250,000.00 | Construction |
| Blast and paint preservation of hull | 1 | lot | $150,000.00 | $150,000.00 | Facilities |
| Blast and paint preservation of freeboard | 1 | lot | $100,000.00 | $100,000.00 | Facilities |
| Blast and paint preservation of exterior decks | 1 | lot | $80,000.00 | $80,000.00 | Facilities |
| Blast and paint preservation of superstructure | 1 | lot | $70,000.00 | $70,000.00 | Facilities |
| Inspection for damage and deterioration (hull, exterior decks, tanks/voids plating and framing) | 1 | lot | $40,000.00 | $40,000.00 | Professional Services |
| Application of new non-skid system to exterior decks | 1 | lot | $60,000.00 | $60,000.00 | Facilities |
| Open, clean, ventilate, inspect, test, and maintain dry each tank/void | 24 | each | $15,000.00 | $360,000.00 | Facilities |
| Partial preservation of ballast tanks/voids | 24 | each | $25,000.00 | $600,000.00 | Facilities |
| Access cover repairs | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Watertight hatch and door repairs | 1 | lot | $35,000.00 | $35,000.00 | Construction |
| Disinfect and certify potable water system | 1 | lot | $15,000.00 | $15,000.00 | Facilities |
| Pump and clean interior surfaces of CHT tank | 1 | lot | $10,000.00 | $10,000.00 | Facilities |
| Main deck repairs | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Hawse hole bulls eye and bolster repairs | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Hull fendering system modifications | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Hot water heater installation | 1 | each | $15,000.00 | $15,000.00 | Facilities |
| Awning replacement | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| A/C plant replacement and backup systems | 1 | lot | $150,000.00 | $150,000.00 | Facilities |
| Switchboard upgrades | 1 | lot | $100,000.00 | $100,000.00 | Facilities |
| 1MC replacement | 1 | lot | $50,000.00 | $50,000.00 | Telecommunications |
| Phone system upgrades | 1 | lot | $40,000.00 | $40,000.00 | Telecommunications |
| CCTV upgrades | 1 | lot | $60,000.00 | $60,000.00 | Security |
| Undocking of vessel | 1 | lot | $15,000.00 | $15,000.00 | Transportation |
| Verification of vessel drawings and provision of redline drawings | 1 | lot | $30,000.00 | $30,000.00 | Professional Services |
| Conduct dock trials | 1 | lot | $20,000.00 | $20,000.00 | Professional Services |
| Coordination and support for all contract requirements (1 year duration) | 1 | year | $5,000,000.00 | $5,000,000.00 | Professional Services |
| Arrangement and coordination for delivery of vessel back to Government | 1 | lot | $15,000.00 | $15,000.00 | Transportation |
| Estimated Bid Value | $12,000,000.00 | ||||