| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Installation of 12" zinc coated ductile iron pipe (DIP) | 2140 | LF | $150.00 | $321,000.00 | Construction |
| Installation of 8" zinc coated ductile iron pipe (DIP) | 1165 | LF | $120.00 | $139,800.00 | Construction |
| Rehabilitation of existing 6-inch cast iron water main via cured-in-place pipe (CIPP) | 310 | LF | $100.00 | $31,000.00 | Construction |
| Tie-in connections to replace existing 6" cast iron water mains | 10 | each | $3,000.00 | $30,000.00 | Construction |
| Tie-in connections to replace existing 4" PVC water mains | 10 | each | $2,500.00 | $25,000.00 | Construction |
| Installation of air release valves | 5 | each | $2,000.00 | $10,000.00 | Construction |
| Installation of fire hydrants | 15 | each | $5,000.00 | $75,000.00 | Construction |
| Installation of service connections | 100 | each | $1,500.00 | $150,000.00 | Construction |
| Abandoning of existing water main | 3500 | LF | $20.00 | $70,000.00 | Construction |
| Abandoning of existing vault | 1 | each | $10,000.00 | $10,000.00 | Construction |
| Abandoning of existing appurtenances | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Surface restoration (slurry seal) | 1 | lot | $300,000.00 | $300,000.00 | Construction |
| Surface restoration (striping) | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Other appurtenances work (general allowance) | 1 | lot | $683,200.00 | $683,200.00 | Construction |
| Estimated Bid Value | $2,000,000.00 | ||||