| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Mobilization for the project | 1 | LS | $150,000.00 | $150,000.00 | Construction |
| All Work on North Ground Storage Tank (isolation, draining, sediment removal, UT coordination, surface prep, hatch addition, equipment removal/replacement, ladder replacement, recoating, disinfection) | 1 | LS | $1,200,000.00 | $1,200,000.00 | Construction |
| All Work on South Ground Storage Tank (isolation, draining, sediment removal, equipment removal/replacement, surface prep, recoating, disinfection) | 1 | LS | $1,000,000.00 | $1,000,000.00 | Construction |
| Replacement steel floor plate, complete in place in either tank | 750 | SF | $150.00 | $112,500.00 | Construction |
| Replacement of steel roof plate, complete in place in either tank | 650 | SF | $120.00 | $78,000.00 | Construction |
| Replacement of structural steel beams, rafters, and roof support members, complete in place in either tank | 7000 | LB | $10.00 | $70,000.00 | Construction |
| Miscellaneous structural steel repairs (brackets, stiffeners, connections, attachments, localized repairs) | 7000 | LB | $12.00 | $84,000.00 | Construction |
| Contingency Allowance 1 for Work Change Directives (miscellaneous) | 1 | LS | $200,000.00 | $200,000.00 | Other |
| Estimated Bid Value | $3,000,000.00 | ||||