| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Demolition of two (2) existing boiler exhaust stacks | 2 | each | $25,000.00 | $50,000.00 | Construction |
| Demolition of one (1) existing generator steam relief stack | 1 | each | $15,000.00 | $15,000.00 | Construction |
| Demolition of concrete/masonry chimney structure | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Sealing of existing roof after demolition | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Construction and installation of two (2) new steel boiler exhaust stacks | 2 | each | $150,000.00 | $300,000.00 | Construction |
| Construction and installation of steel support structure for new stacks | 1 | lot | $170,000.00 | $170,000.00 | Construction |
| Construction and installation of one (1) new steel generator exhaust pipe | 1 | each | $40,000.00 | $40,000.00 | Construction |
| Project Management, Supervision, Labor, Tools, and Equipment (overall project execution) | 1 | lot | $80,000.00 | $80,000.00 | Construction |
| Estimated Bid Value | $750,000.00 | ||||