| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Repair and Reconstruction of Auxiliary Spillway | 1 | lot | $120,000.00 | $120,000.00 | Construction |
| Restoration of Overtopped Embankment Sections to Original Design Dimensions | 1 | lot | $80,000.00 | $80,000.00 | Construction |
| Excavation and Removal of Eroded Alluvium | 500 | cubic yard | $35.00 | $17,500.00 | Construction |
| Excavation and Removal of Gullies | 300 | cubic yard | $40.00 | $12,000.00 | Construction |
| Excavation and Removal of Unsuitable Materials | 400 | cubic yard | $38.00 | $15,200.00 | Construction |
| Construction and Preparation of Approved Subgrade | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Estimated Bid Value | $275,000.00 | ||||