| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Demolition of existing storm drain | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Demolition of existing curb and gutter | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Demolition of existing driveway aprons | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Demolition of existing driveways | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Demolition of existing trees | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Installation of storm drain pipes and structures | 1 | lot | $750,000.00 | $750,000.00 | Construction |
| Excavation and grading of existing open drainage channel | 1 | lot | $400,000.00 | $400,000.00 | Construction |
| Adjustment and installation of water appurtenances | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Relocation of water service lines | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Relocation of sanitary sewer service lines | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Installation of curb and gutter | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Installation of sidewalk | 1 | lot | $120,000.00 | $120,000.00 | Construction |
| Installation of driveway aprons | 1 | lot | $80,000.00 | $80,000.00 | Construction |
| Installation of driveways | 1 | lot | $90,000.00 | $90,000.00 | Construction |
| Milling and surfacing with associated restriping of traffic control markings | 1 | lot | $600,000.00 | $600,000.00 | Construction |
| Removal and replacement of fences | 1 | lot | $40,000.00 | $40,000.00 | Construction |
| Installation of sediment and erosion control devices | 1 | lot | $60,000.00 | $60,000.00 | Construction |
| Clearing and grubbing | 1 | lot | $35,000.00 | $35,000.00 | Construction |
| Restoration of disturbed areas (landscaping, seeding, etc.) | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Traffic control services | 1 | lot | $80,000.00 | $80,000.00 | Construction |
| As-built record drawings | 1 | lot | $25,000.00 | $25,000.00 | Professional Services |
| Project Management and Supervision (General Construction Services) | 1 | lot | $500,000.00 | $500,000.00 | Construction |
| Estimated Bid Value | $3,500,000.00 | ||||