| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| VRF fan coil units | 8 | each | $3,500.00 | $28,000.00 | Construction |
| VRF condensers | 3 | each | $15,000.00 | $45,000.00 | Construction |
| Heat pump rooftop unit (RTU) | 1 | each | $50,000.00 | $50,000.00 | Construction |
| New main distribution power panel | 1 | each | $10,000.00 | $10,000.00 | Construction |
| Ductwork installation (labor and materials) | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| Piping installation (labor and materials) | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Insulation installation (labor and materials) | 1 | lot | $40,000.00 | $40,000.00 | Construction |
| Pumps installation (labor and materials) | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Power and controls wiring installation (labor and materials) | 1 | lot | $80,000.00 | $80,000.00 | Construction |
| Controls integration into existing building management system | 1 | lot | $60,000.00 | $60,000.00 | Construction |
| Project supervision and management | 1 | lot | $100,000.00 | $100,000.00 | Professional Services |
| Balancing and commissioning | 1 | lot | $25,000.00 | $25,000.00 | Professional Services |
| Prevailing Wage Labor (overall project cost factor) | 1 | lot | $67,000.00 | $67,000.00 | Construction |
| Estimated Bid Value | $750,000.00 | ||||