| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Preparation and Implementation of the Erosion and Sediment Pollution Control Plan | 1 | L.S. | $25,000.00 | $25,000.00 | Construction |
| Clearing and Grubbing | 1 | L.S. | $30,000.00 | $30,000.00 | Construction |
| Trench Excavation | 2575 | C.Y. | $40.00 | $103,000.00 | Construction |
| Subsurface Drain – Eight-Inch (8”) Nominal Diameter Perforated PVC SDR-35 Pipe | 1088 | L.F. | $35.00 | $38,080.00 | Construction |
| Subsurface Drain – Eight-Inch (8”) Nominal Diameter Solid PVC SDR-35 Pipe | 78 | L.F. | $30.00 | $2,340.00 | Construction |
| Subsurface Drain – AASHTO No. 1 Coarse Aggregate | 3680 | C.Y. | $60.00 | $220,800.00 | Construction |
| Subsurface Drain – AASHTO No. 57 Coarse Aggregate | 173 | C.Y. | $55.00 | $9,515.00 | Construction |
| Subsurface Drain – Precast Concrete Inlet | 1 | EACH | $1,500.00 | $1,500.00 | Construction |
| Subsurface Drain – Precast Concrete Manhole | 1 | EACH | $3,000.00 | $3,000.00 | Construction |
| Segmented Retaining Wall with Geogrid Reinforcement - Retaining Wall | 3150 | S.F. | $150.00 | $472,500.00 | Construction |
| Segmented Retaining Wall with Geogrid Reinforcement - Eight-Inch (8") Nominal Diameter Perforated PVC SDR-35 Pipe | 898 | L.F. | $35.00 | $31,430.00 | Construction |
| Concrete Patio Replacement | 250 | S.Y. | $120.00 | $30,000.00 | Construction |
| Site Restoration – Seeding | 1 | L.S. | $10,000.00 | $10,000.00 | Construction |
| Site Restoration – Topsoil | 20 | TON | $50.00 | $1,000.00 | Construction |
| Site Restoration – Miscellaneous | 1 | L.S. | $40,000.00 | $40,000.00 | Construction |
| Estimated Bid Value | $1,120,000.00 | ||||