| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Abandonment of old well | 1 | each | $5,000.00 | $5,000.00 | Construction |
| New plumbing system installation (including AWWA C-509 valves, AWWA flange fittings, Watts 2" pressure reducer, 2" flange master meter, Stenner model 45MHP10 chemical pump, 3 phase air compressor, accessories and fittings) | 1 | lot | $35,000.00 | $35,000.00 | Construction |
| 30'x50' pre-fabricated metal Red Iron open span building (12' tall eaves, 26-gauge roof & walls, 1 roll-up door, 1 3'x7' walk-through door, insulation, gutters, engineer's stamped drawings, anchor bolt plans) | 1 | each | $100,000.00 | $100,000.00 | Construction |
| Sand blasting and painting of tank (1 coat Tnemec-Zinc 3-5ml inside and out, 2nd coat inside Tnemec series 21 6-9ml, 3rd coat inside Tnemec series 216-9ml, 2nd coat outside L140 epoxy 6-9ml, 3rd coat outside 1094 urethane 5-7ml) | 1 | each | $40,000.00 | $40,000.00 | Construction |
| New electrical system installation (200-amp enclosed circuit breaker outside, 200-amp main breaker panel inside, pump control panel with motor starter, disconnect at well, 6x 8" long LED strip lights, 2x 55 watt outside lights with photocell, 10x 120V outlets including outside GFCI, 3 phase circuit for air compressor, reconnect existing pressure controls on tank) | 1 | lot | $60,000.00 | $60,000.00 | Construction |
| Supervision, labor, tools, and equipment for purchase and installation (overall project management) | 1 | lot | $80,000.00 | $80,000.00 | Professional Services |
| Estimated Bid Value | $320,000.00 | ||||