| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Design-Bid-Build Construction Project for P110 Cape Canaveral Railhead and Transfer Facilities | 1 | lot | $62,500,000.00 | $62,500,000.00 | Construction |
| Construction of Railroad Trackage (connecting commercial rail to on-base processing facility) | 1 | lot | $20,000,000.00 | $20,000,000.00 | Construction |
| Construction of Low-Rise Open Air Standing Seam-Metal Roofed Canopy (Submarine Launched Ballistic Missile Processing Facility / Motor Transfer Facility) | 1 | lot | $40,000,000.00 | $40,000,000.00 | Construction |
| Reinforced Shallow Foundation with Wide-Flange Beams and Columns and Continuous Footings (for Motor Transfer Facility) | 1 | lot | $1,000,000.00 | $1,000,000.00 | Construction |
| Superflat Floors for Air Pallet Operations (within Motor Transfer Facility) | 1 | lot | $500,000.00 | $500,000.00 | Construction |
| Sloped, Uninsulated Metal Roof Panels on Steel Joists (for Motor Transfer Facility) | 1 | lot | $1,000,000.00 | $1,000,000.00 | Construction |
| Estimated Bid Value | $62,500,000.00 | ||||