| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Removal of existing electric tanked water heater | 1 | lot | $500.00 | $500.00 | Construction |
| Navien NPE-240A2 tankless water heater | 4 | each | $2,000.00 | $8,000.00 | Facilities |
| Installation of four (4) Navien NPE-240A2 tankless water heaters | 1 | lot | $8,000.00 | $8,000.00 | Construction |
| Isolation of commercial kitchen hot water system | 1 | lot | $1,000.00 | $1,000.00 | Construction |
| Removal of external recirculation pump in commercial kitchen | 1 | lot | $500.00 | $500.00 | Construction |
| Integration of internal recirculation pumps (existing and new units) | 1 | lot | $2,000.00 | $2,000.00 | Construction |
| Installation of external recirculation loop for the rest of the building | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Insulation of all hot water piping | 1 | lot | $4,000.00 | $4,000.00 | Construction |
| Insulation of cold water piping in conditioned spaces | 1 | lot | $2,000.00 | $2,000.00 | Construction |
| Scissor lift rental and operation | 1 | lot | $1,500.00 | $1,500.00 | Facilities |
| Safe partitioning of work areas and hallway access maintenance | 1 | lot | $1,000.00 | $1,000.00 | Construction |
| Project management and coordination (working around class schedules, minimizing disruption) | 1 | lot | $3,000.00 | $3,000.00 | Professional Services |
| Permit acquisition and coordination of inspections | 1 | lot | $2,500.00 | $2,500.00 | Professional Services |
| Labor for system assembly and installation (excluding specific unit installation) | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Contingency/Miscellaneous materials and services | 1 | lot | $8,000.00 | $8,000.00 | Other |
| Estimated Bid Value | $70,000.00 | ||||