| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Overall Construction Management and Supervision for Gate 7 Parking Garage | 1 | lot | $15,000,000.00 | $15,000,000.00 | Construction |
| Site Development, Clearing, Grading, Excavation, and Civil Infrastructure Improvements | 1 | lot | $8,000,000.00 | $8,000,000.00 | Construction |
| Utility Relocations, Extensions, Tie-ins, and Connections | 1 | lot | $5,000,000.00 | $5,000,000.00 | Construction |
| Substructure Construction (Foundations, Slab-on-Grade, Excavation Support, Waterproofing, Retaining Walls) | 1 | lot | $12,000,000.00 | $12,000,000.00 | Construction |
| Parking Garage Structure (Structural Framing, Parking Decks, Ramps, Stairs, Elevators, Roof Assemblies) | 1 | lot | $30,000,000.00 | $30,000,000.00 | Construction |
| Mechanically Ventilated Parking Garage Systems (Equipment, Ductwork, Controls, Electrical, Life-Safety) | 1 | lot | $7,000,000.00 | $7,000,000.00 | Construction |
| Exterior Façade and Building Envelope Construction (Classical Architectural Brick Façade, Openings) | 1 | lot | $10,000,000.00 | $10,000,000.00 | Construction |
| Exterior Doors, Windows, Louvers, Waterproofing, Sealants, Flashings | 1 | lot | $4,000,000.00 | $4,000,000.00 | Construction |
| Mechanical, Electrical, Plumbing, Fire Protection, Fire Alarm Systems | 1 | lot | $15,000,000.00 | $15,000,000.00 | Construction |
| Emergency Communications, Lighting, Controls, IT, Telecommunications, Electronic Security, Access Control, CCTV, Parking Guidance Systems | 1 | lot | $8,000,000.00 | $8,000,000.00 | Security |
| Physical Security Elements (Vehicle Barriers, Bollards, Gates, Credentialing Areas, Screening Infrastructure) | 1 | lot | $6,000,000.00 | $6,000,000.00 | Security |
| Roadway, Shuttle, Pedestrian Circulation, Hardscape, Landscape, Site Lighting, Signage, and Site Improvements | 1 | lot | $7,000,000.00 | $7,000,000.00 | Construction |
| Stormwater Management Facilities, Erosion and Sediment Control, Environmental Protection Measures | 1 | lot | $3,000,000.00 | $3,000,000.00 | Construction |
| Testing, Inspections, Commissioning Support, Training, Warranties, As-Built Documentation, BIM/COBie Deliverables, Project Closeout | 1 | lot | $3,000,000.00 | $3,000,000.00 | Professional Services |
| Estimated Bid Value | $125,000,000.00 | ||||
Sign up free to see the original bid posting link, plus the 12 documents, contracting-officer contacts and AI response outlines. Every feature is free through December 31, 2026.