| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Base Bid: Placement of berm fill material along 7,000 feet of construction baseline | 820000 | cubic yards | $15.00 | $12,300,000.00 | Construction |
| Optional Bid Items: Placement of additional berm fill material along Front Beach area | 673000 | cubic yards | $15.00 | $10,095,000.00 | Construction |
| Dredging material from approved offshore borrow area (for Base Bid and Optional Bid items) | 1493000 | cubic yards | $5.00 | $7,465,000.00 | Construction |
| Environmental restrictions compliance and monitoring | 1 | lot | $500,000.00 | $500,000.00 | Professional Services |
| Beach tilling | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Project Management and Mobilization/Demobilization | 1 | lot | $1,000,000.00 | $1,000,000.00 | Professional Services |
| Estimated Bid Value | $17,500,000.00 | ||||