| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Horizontal Cartridge Filtration System | 2 | each | $75,000.00 | $150,000.00 | Construction |
| Associated Piping, Fittings, Appurtenances, and Structural Pipe Supports | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Excavation and Disposal of Excess Excavated Materials | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Freight and Delivery to Project Site | 1 | lot | $10,000.00 | $10,000.00 | Transportation |
| Manufacturer Warranties | 1 | lot | $5,000.00 | $5,000.00 | Professional Services |
| Operation and Maintenance Manuals | 1 | lot | $2,500.00 | $2,500.00 | Professional Services |
| Shop and Field Testing | 1 | lot | $15,000.00 | $15,000.00 | Professional Services |
| Manufacturer-Provided On-Site Services (Installation/Commissioning Support) | 1 | lot | $25,000.00 | $25,000.00 | Professional Services |
| General Labor and Equipment for System Installation | 1 | lot | $60,000.00 | $60,000.00 | Construction |
| Project Management and Supervision | 1 | lot | $12,500.00 | $12,500.00 | Professional Services |
| Estimated Bid Value | $350,000.00 | ||||