| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Decommissioning and abandoning existing Well 4 | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Installation and commissioning of Town-furnished 75 HP submersible pump, motor, and pitless adapter | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Furnish and install approximately 150 linear feet of 8-inch ductile iron raw water main to Glenwood Road Water Treatment Plant (GRWTP) | 150 | linear feet | $300.00 | $45,000.00 | Construction |
| Furnish and install process piping, valves, and one raw water hydrant | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Selective demolition | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Electrical, instrumentation, controls, and SCADA integration work | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Chain link fencing installation | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Paving restoration | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Site restoration | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Incidental work as described in Contract Documents (Well 4R Implementation Project Management and General Conditions) | 1 | lot | $280,000.00 | $280,000.00 | Construction |
| Estimated Bid Value | $750,000.00 | ||||