| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Asphalt milling and overlay | 20000 | square yard | $25.00 | $500,000.00 | Construction |
| Seal coat application | 20000 | square yard | $3.00 | $60,000.00 | Construction |
| Base and pavement replacement | 5000 | square yard | $75.00 | $375,000.00 | Construction |
| Cleaning and sealing joints and cracks | 5000 | linear foot | $5.00 | $25,000.00 | Construction |
| Curb ramps (ADA compliant) | 20 | each | $3,000.00 | $60,000.00 | Construction |
| Concrete curbs | 1000 | linear foot | $40.00 | $40,000.00 | Construction |
| Sidewalks (concrete) | 500 | square foot | $15.00 | $7,500.00 | Construction |
| Driveways (concrete) | 10 | each | $2,500.00 | $25,000.00 | Construction |
| Concrete retaining walls - combination type | 50 | linear foot | $200.00 | $10,000.00 | Construction |
| Speed humps | 5 | each | $4,000.00 | $20,000.00 | Construction |
| Topsoil application | 100 | cubic yard | $50.00 | $5,000.00 | Construction |
| Sodding | 1000 | square yard | $8.00 | $8,000.00 | Construction |
| Signage (traffic and street signs) | 20 | each | $300.00 | $6,000.00 | Construction |
| Pavement markings installation | 5000 | linear foot | $2.00 | $10,000.00 | Construction |
| Adjusting existing valve boxes | 30 | each | $250.00 | $7,500.00 | Construction |
| Adjusting existing meter boxes | 20 | each | $200.00 | $4,000.00 | Construction |
| Adjusting existing manholes | 15 | each | $500.00 | $7,500.00 | Construction |
| Contingency for unforeseen site conditions | 1 | lot | $300,000.00 | $300,000.00 | Other |
| Estimated Bid Value | $1,500,000.00 | ||||