| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Replacement of cathodic protection system for Tank 62501E | 1 | each | $150,000.00 | $150,000.00 | Construction |
| Replacement of cathodic protection system for Tank 62501W | 1 | each | $150,000.00 | $150,000.00 | Construction |
| Replacement of electrical system for raised platform (Tanks 62501E & 62501W) | 1 | lot | $80,000.00 | $80,000.00 | Construction |
| Strip and replace interior protective coating for Tank 62501E | 1 | each | $200,000.00 | $200,000.00 | Construction |
| Strip and replace interior protective coating for Tank 62501W | 1 | each | $200,000.00 | $200,000.00 | Construction |
| Strip and replace protective coating for piping to 4 valves (Tanks 62501E & 62501W) | 1 | lot | $70,000.00 | $70,000.00 | Construction |
| Clean and recoat exterior stairs (Tanks 62501E & 62501W) | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Clean and recoat raised platform and its structures (Tanks 62501E & 62501W) | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| Project Management and Site Supervision (Rehab Tanks 62501E & 62501W) | 1 | lot | $200,000.00 | $200,000.00 | Professional Services |
| Estimated Bid Value | $1,200,000.00 | ||||