| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| 18-inch RCP storm drain pipe | 1832 | LF | $120.00 | $219,840.00 | Construction |
| 24-inch RCP storm drain pipe | 62 | LF | $150.00 | $9,300.00 | Construction |
| 36-inch RCP storm drain pipe | 53 | LF | $250.00 | $13,250.00 | Construction |
| 48-inch RCP storm drain pipe | 42 | LF | $350.00 | $14,700.00 | Construction |
| New storm drainage structures (curb inlets, ditch inlets, grate inlets, storm manholes) | 31 | each | $3,500.00 | $108,500.00 | Construction |
| New 1x1 yard inlets | 6 | each | $1,200.00 | $7,200.00 | Construction |
| Conflict/junction boxes | 2 | each | $4,000.00 | $8,000.00 | Construction |
| Utility service conflicts resolution | 10 | each | $2,000.00 | $20,000.00 | Construction |
| 6x24 inch concrete curb and gutter | 6548 | LF | $25.00 | $163,700.00 | Construction |
| Concrete driveway replacement | 398 | SY | $75.00 | $29,850.00 | Construction |
| Class A concrete removal and replacement | 512 | SY | $80.00 | $40,960.00 | Construction |
| Recycled asphalt concrete leveling | 309 | TONS | $120.00 | $37,080.00 | Construction |
| 9.5mm Superpave asphalt resurfacing | 600 | TONS | $150.00 | $90,000.00 | Construction |
| Striping | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Erosion control | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Grading and clearing within drainage easement | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Traffic control | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Project management and general conditions | 1 | lot | $200,000.00 | $200,000.00 | Professional Services |
| Estimated Bid Value | $1,120,600.00 | ||||