| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| General Construction - Selective Demolition of Support Areas | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| General Construction - Roof Repair | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| General Construction - GWB Wall Work | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| General Construction - Removal/Reinstallation of Existing ACT Ceiling | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| HVAC Construction - Selective Demolition | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| HVAC Construction - New Fan Coils | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| HVAC Construction - New Pumps | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| HVAC Construction - New Piping | 1 | lot | $100,000.00 | $100,000.00 | Construction |
| HVAC Construction - Piping Insulation | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| HVAC Construction - New HVAC Equipment (general) | 1 | lot | $150,000.00 | $150,000.00 | Construction |
| HVAC Construction - Building Controls System | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Electrical Work - Selective Demolition | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Electrical Work - New Circuits for HVAC Equipment | 1 | lot | $80,000.00 | $80,000.00 | Construction |
| Estimated Bid Value | $750,000.00 | ||||