| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Modification of existing far side movable grating HPU starter box | 1 | each | $7,500.00 | $7,500.00 | Construction |
| Installation of new PLC control cabinet on Pier 1N | 1 | each | $25,000.00 | $25,000.00 | IT Hardware |
| Installation of new PLC control cabinet on far side span lock platform | 1 | each | $25,000.00 | $25,000.00 | IT Hardware |
| Removal of existing fully seated movable grating limit switches | 1 | lot | $2,000.00 | $2,000.00 | Construction |
| Installation of new movable grating fully seated limit switches | 1 | lot | $8,000.00 | $8,000.00 | IT Hardware |
| Installation of new fully raised movable grating limit switches | 1 | lot | $8,000.00 | $8,000.00 | IT Hardware |
| Installation of new rotary cam limit switch at far side span lock platform | 1 | each | $3,500.00 | $3,500.00 | IT Hardware |
| Integration of new equipment into existing PLC and control system | 1 | lot | $44,000.00 | $44,000.00 | IT Services |
| Estimated Bid Value | $125,000.00 | ||||