| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Removal and disposal of existing cedar roofing and associated components | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Inspection of roof sheathing | 1 | lot | $1,000.00 | $1,000.00 | Construction |
| Replacement of deteriorated roof sheathing (as authorized) | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Installation of compatible underlayment and ice and water barrier | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Installation of synthetic cedar shake roofing system (materials and labor) | 1 | lot | $90,000.00 | $90,000.00 | Construction |
| Installation of starter, ridge, hip, valley, edge, and accessory components for roofing system | 1 | lot | $8,000.00 | $8,000.00 | Construction |
| Installation of flashing and drip edge | 1 | lot | $4,000.00 | $4,000.00 | Construction |
| Installation of ventilation components | 1 | lot | $2,000.00 | $2,000.00 | Construction |
| Installation/sealing of exhaust and piping penetrations | 1 | lot | $1,500.00 | $1,500.00 | Construction |
| Temporary protection and site protection during work | 1 | lot | $3,000.00 | $3,000.00 | Construction |
| Debris removal and site cleanup | 1 | lot | $2,000.00 | $2,000.00 | Construction |
| Restoration of property damaged by the Work | 1 | lot | $1,500.00 | $1,500.00 | Construction |
| Permits and incidentals | 1 | lot | $2,000.00 | $2,000.00 | Construction |
| Estimated Bid Value | $150,000.00 | ||||