| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Demolition of two (2) existing boiler exhaust stacks | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Demolition of one (1) existing generator steam relief stack | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Demolition of concrete/masonry chimney structure | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Sealing of existing roof after demolition | 1 | lot | $7,500.00 | $7,500.00 | Construction |
| Construction and installation of two (2) new steel boiler exhaust stacks | 2 | each | $25,000.00 | $50,000.00 | Construction |
| Construction and installation of steel support structure for new stacks | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Construction and installation of one (1) new steel generator exhaust pipe | 1 | each | $17,500.00 | $17,500.00 | Construction |
| Estimated Bid Value | $125,000.00 | ||||
Sign up free to see the agency name and the original bid posting link, plus the 7 documents, contracting-officer contacts and AI response outlines. Every feature is free through December 31, 2026.