Most recent contracts from Department of Energy under NAICS 237130, last 3 years. Typical award: $374K.
| FOUR TRIBES CIVIL CONSTRUCTION LLC | $374K | Sep 2026 | Eo 14398, keswick substation and redding maintenance facility cable and waveguide bridge β¦ details |
| SITE WORK SOLUTIONS | $95K | Sep 2026 | Western area power administration (wapa) requirement to repair two (2) automated sliding β¦ details |
| COMPLETE CONCRETE, INC. | $564K | Sep 2026 | Cheyenne area comm building electrical repairs details |
| COMPLETE CONCRETE, INC. | $79K | Sep 2026 | Midland repeater - erosion and fence repair project, south dakota details |
| ADDISON CONSTRUCTION CO | $442K | Sep 2026 | The stegall substation stage 07 phase 01 project to replace end of life equipment and ins⦠details |
Source: USAspending.gov. Similar work, not necessarily this exact contract.
| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| General Contractor Services for Kautz Road Substation Rebuild and Renovation | 1 | lot | $20,000,000.00 | $20,000,000.00 | Construction |
| Project Management and Supervision (including safety and quality control oversight) | 1 | lot | $2,500,000.00 | $2,500,000.00 | Professional Services |
| Labor for Substation Construction | 1 | lot | $1,500,000.00 | $1,500,000.00 | Construction |
| Materials and Equipment Procurement for Substation (excluding prefabricated control house) | 1 | lot | $500,000.00 | $500,000.00 | Construction |
| Transportation and Logistics | 1 | lot | $250,000.00 | $250,000.00 | Transportation |
| Bonding Costs | 1 | lot | $250,000.00 | $250,000.00 | Professional Services |
| Estimated Bid Value | $25,000,000.00 | ||||