Responses are due December 8, 2026 at 9:00 AM (local agency time). That is 33 days from today.
Virginia. It is listed with other open Virginia government bids on BidsNexus.
No set-aside is listed on the notice. Check the solicitation documents for vendor registration and eligibility requirements.
NAICS 236220 (Construction).
Solicitation in the Construction category.
Responses go through the agency's official posting on sam.gov. BidsNexus links to the original solicitation and its documents; a free account shows the link and emails you similar bids.
Most recent contracts from Department of Veterans Affairs under NAICS 236220, last 3 years. Typical award: $2.1M.
| LC FLUHARTY CONSTRUCTION LLC | $14.9M | Dec 2026 | Project 541-19-101 renovate operating room - vamc cleveland eo 14398 details |
| KMK CONSTRUCTION, INC | $1.5M | Nov 2026 | 631-26-012 transformer replacement. details |
| HIRT ELECTRIC, LLC | $244K | Nov 2026 | Hq guidance - commercial clauses for open market construction & a/e details |
| U.S. VET GENERAL CONTRACTING, LLC | $2.6M | Nov 2026 | Task order for facility condition improvements under the construction multiple award task⦠details |
| U.S. VET GENERAL CONTRACTING, LLC | $2.1M | Nov 2026 | Task order #13 for 3yr pmi under the construction multiple award task order contract (mat⦠details |
Source: USAspending.gov. Similar work, not necessarily this exact contract.
| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| New electrical entrance building (slab on grade, brick on CMU wall, slate roof tile) | 1 | each | $750,000.00 | $750,000.00 | Construction |
| Medium voltage loop replacement (concrete encased duct bank with new cables) | 300 | linear foot | $500.00 | $150,000.00 | Construction |
| Demolition and removal of old VA owned medium voltage entrance metal shack | 1 | each | $25,000.00 | $25,000.00 | Construction |
| Replacement of medium voltage sectionalized switch | 1 | each | $150,000.00 | $150,000.00 | Construction |
| New metal-clad switchgear with draw-out vacuum circuit breakers | 1 | each | $500,000.00 | $500,000.00 | Construction |
| Replacement of medium voltage oil filled transformer | 1 | each | $200,000.00 | $200,000.00 | Construction |
| Replacement of Normal (service entrance) Switchboards | 2 | each | $150,000.00 | $300,000.00 | Construction |
| Replacement of Generator switchboards | 2 | each | $100,000.00 | $200,000.00 | Construction |
| Replacement of Automatic transfer switches | 7 | each | $50,000.00 | $350,000.00 | Construction |
| Replacement of Distribution Panels | 5 | each | $25,000.00 | $125,000.00 | Construction |
| Replacement of Panelboards | 68 | each | $10,000.00 | $680,000.00 | Construction |
| Replacement of undersized feeders (labor and materials for multiple circuits) | 1 | lot | $1,500,000.00 | $1,500,000.00 | Construction |
| Installation of redundant equipment grounding conductor (100,000 sq ft of existing electrical branch circuit distribution) | 100000 | square foot | $20.00 | $2,000,000.00 | Construction |
| Rerouting of sewer piping (vertical and horizontal) | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Rerouting of hot water piping (vertical and horizontal) | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Installation of exhaust fan to new Medium Voltage building | 1 | each | $15,000.00 | $15,000.00 | Construction |
| Identification tagging for new and existing electrical equipment | 100 | each | $50.00 | $5,000.00 | Facilities |
| Cleaning debris from existing electrical enclosures | 30 | each | $200.00 | $6,000.00 | Facilities |
| Correcting panel grounding (terminate cable directly to existing panel's ground bar) | 30 | each | $500.00 | $15,000.00 | Construction |
| Phasing plan development and approval | 1 | lot | $100,000.00 | $100,000.00 | Professional Services |
| Temporary power solutions to minimize electrical outages | 1 | lot | $500,000.00 | $500,000.00 | Construction |
| Project Management and Supervision (1,174 calendar days) | 1 | lot | $3,000,000.00 | $3,000,000.00 | Professional Services |
| Contingency and unforeseen conditions (approx. 10-15% of base construction) | 1 | lot | $1,500,000.00 | $1,500,000.00 | Other |
| Estimated Bid Value | $12,000,000.00 | ||||