| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Mobilization | 1 | L.S. | — | — | Mobilization |
| Traffic Control | 1 | L.S. | — | — | Traffic Control |
| Clearing and Grubbing - General | 1 | L.S. | — | — | Clearing and Grubbing |
| Clearing and Grubbing Trees Over 9" to 18" Diameter | 5 | EA. | — | — | Clearing and Grubbing |
| Clearing and Grubbing Trees Over 18" to 27" Diameter | 1 | EA. | — | — | Clearing and Grubbing |
| Clearing and Grubbing Trees Over 27" to 36" Diameter | 1 | EA. | — | — | Clearing and Grubbing |
| Remove Pavement | 2880 | S.Y. | — | — | Demolition |
| Remove Gravel Surfacing | 975 | S.Y. | — | — | Demolition |
| Remove Sidewalk | 450 | S.F. | — | — | Demolition |
| Remove 15" to 18" Storm Sewer Pipe | 25 | L.F. | — | — | Demolition |
| Remove 36" Storm Sewer Pipe | 30 | L.F. | — | — | Demolition |
| Remove 42" Storm Sewer Pipe | 350 | L.F. | — | — | Demolition |
| Remove Wood Bollard Posts | 21 | EA. | — | — | Demolition |
| Remove Existing Ball Field Bleachers and Dugout Benches | 1 | L.S. | — | — | Demolition |
| Remove Existing Ball Park Fencing | 1 | L.S. | — | — | Demolition |
| Remove Existing Light Pole and Overhead Power Lines | 1 | L.S. | — | — | Demolition |
| Common Earthwork, In Place | 4500 | C.Y. | — | — | Earthwork |
| Topsoil (Moved Twice), Established Quantity | 5000 | C.Y. | — | — | Earthwork |
| Install Silt Fence | 1330 | L.F. | — | — | Erosion Control |
| Install Seeding - Type B, In Place | 6080 | S.Y. | — | — | Landscaping |
| Install Rolled Erosion Control, Type I with Seeding - Type B, In Place | 2330 | S.Y. | — | — | Erosion Control |
| Temporary Seeding Mix, In Place | 20000 | S.Y. | — | — | Landscaping |
| Install Wattle (12" diameter) | 60 | L.F. | — | — | Erosion Control |
| Install Area Inlet Protection | 2 | EA. | — | — | Erosion Control |
| Install Curb Inlet Protection | 3 | EA. | — | — | Erosion Control |
| Install Construction Entrance | 2 | EA. | — | — | Erosion Control |
| Install Concrete Washout | 1 | EA. | — | — | Erosion Control |
| Stormwater Pollution Prevention Plan (SWPPP) Maintenance Allowance | 1 | L.S. | — | — | Stormwater Management |
| Construct Aggregate Bedding for Type R2 , 6" HDPE Downspout Pipe | 50 | L.F. | — | — | Storm Sewer |
| Construct Aggregate Bedding for Type R2 , 12" Storm Sewer Pipe | 65 | L.F. | — | — | Storm Sewer |
| Construct Aggregate Bedding for Type R2 , 15" Storm Sewer Pipe | 16 | L.F. | — | — | Storm Sewer |
| Construct Aggregate Bedding for Type R2 , 18" Storm Sewer Pipe | 555 | L.F. | — | — | Storm Sewer |
| Construct Aggregate Bedding for Type R2 , 24" Storm Sewer Pipe | 40 | L.F. | — | — | Storm Sewer |
| Construct Aggregate Bedding for Type R2 , 36" Storm Sewer Pipe | 410 | L.F. | — | — | Storm Sewer |
| Construct Aggregate Bedding for Type R2 , 42" Storm Sewer Pipe | 80 | L.F. | — | — | Storm Sewer |
| Construct 6” I.D. H.D.P.E Pipe For Downspout, In Place | 50 | L.F. | — | — | Storm Sewer |
| Construct 12” I.D. R.C.P., Class III, In Place | 65 | L.F. | — | — | Storm Sewer |
| Construct 15” I.D. R.C.P., Class III, In Place | 16 | L.F. | — | — | Storm Sewer |
| Construct 18” I.D. R.C.P., Class III, In Place | 555 | L.F. | — | — | Storm Sewer |
| Construct 24” I.D. R.C.P., Class III, In Place | 40 | L.F. | — | — | Storm Sewer |
| Construct 36” I.D. R.C.P., Class III, In Place | 410 | L.F. | — | — | Storm Sewer |
| Construct 42” I.D. R.C.P., Class III, In Place | 80 | L.F. | — | — | Storm Sewer |
| Construct 15" R.C.P. Flared End Section with Bar Grates, In Place | 1 | EA. | — | — | Storm Sewer |
| Construct 42" R.C.P. Flared End Section with Bar Grates, In Place | 1 | EA. | — | — | Storm Sewer |
| Construct 48" I.D. Storm Sewer Manhole, In Place | 7 | V.F. | — | — | Storm Sewer |
| Construct 54" I.D. Storm Sewer Manhole, In Place | 6 | V.F. | — | — | Storm Sewer |
| Construct 72" I.D. Storm Sewer Manhole, In Place | 15 | V.F. | — | — | Storm Sewer |
| Construct 84" I.D. Storm Sewer Manhole, In Place | 26 | V.F. | — | — | Storm Sewer |
| Construct Curb Inlet - Type I , In Place | 1 | EA. | — | — | Storm Sewer |
| Construct Curb Inlet - Type III , In Place | 2 | EA. | — | — | Storm Sewer |
| Construct Area Inlet - Type II | 2 | EA. | — | — | Storm Sewer |
| Modify Existing Curb Inlet Structure and replace with 3 Saddle-Creek Inlets, In Place | 1 | L.S. | — | — | Storm Sewer |
| Construct Type B Rip-Rap, In Place | 50 | TON | — | — | Erosion Control |
| Construct Flex-a-Mat Apron, In Place | 100 | S.F. | — | — | Erosion Control |
| Install Frame and Solid Storm Manhole Cover, In Place | 7 | EA. | — | — | Storm Sewer |
| Construct 6" Storm Sewer Pipe Plug (Downspouts), In Place | 1 | EA. | — | — | Storm Sewer |
| Construct 18" Storm Sewer Pipe Plug, In Place | 2 | EA. | — | — | Storm Sewer |
| Construct Concrete Pipe Collar, In Place | 1 | EA. | — | — | Storm Sewer |
| Construct 9" Concrete Pavement (Type 47B-3500), In Place | 200 | S.Y. | — | — | Paving |
| Construct 8" Concrete Pavement (Type 47B-3500), In Place | 6840 | S.Y. | — | — | Paving |
| Construct 6" Concrete Sidewalk Pavement (Type 47B-3500), In Place | 1890 | S.Y. | — | — | Paving |
| Subgrade Preparation, In Place | 3550 | C.Y. | — | — | Earthwork |
| Permanent Paint Marking, 5" White, In Place | 3220 | L.F. | — | — | Pavement Markings |
| Permanent Paint Pavement Marking Symbol (White), In Place | 6 | EA. | — | — | Pavement Markings |
| Construct PCC Curb Ramp, In Pl | — | — | Paving |