Responses are due November 19, 2026 at 5:00 PM (local agency time). That is 9 days from today.
Minnesota. It is listed with other open Minnesota government bids on BidsNexus.
The notice sets this opportunity aside for Small Business businesses. Confirm eligibility in the solicitation documents.
NAICS 237130 (Construction).
Request for Information (RFI) in the Construction category.
Responses go through the agency's official posting on sam.gov. BidsNexus links to the original solicitation and its documents; a free account shows the link and emails you similar bids.
Most recent contracts from Department of the Army under NAICS 237130, last 3 years. Typical award: $136K.
| MISCELLANEOUS FOREIGN AWARDEES | $3M | Jul 2026 | //this is a contract executed under the host nation abg75 construction program. acws ver… details |
| BAHR ELECTRIC LLC | $51K | Jun 2026 | Task order on outside cable plant idiq - provide fiber optic and copper telecommunication… details |
| CCI FACILITY SUPPORT SERVICES LLC | $271K | May 2026 | Power reliability enhancement program (prep) engineering support to perform testing and m… details |
| BAHR ELECTRIC LLC | $16K | May 2026 | Task order on outside cable plant idiq - provide fiber optic and copper telecommunication… details |
| GLOBAL ENGINEERING SERVICES INC | $136K | May 2026 | Work shall consist of the installation of a critical electrical line to building 35 commu… details |
Source: USAspending.gov. Similar work, not necessarily this exact contract.
| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Maintain/refeed single-phase 120/240-volt transformer for lighting, gage house, and toilet area | 1 | job | $15,000.00 | $15,000.00 | Construction |
| Supply and install multiple utility poles (likely from the south heading north) | 5 | each | $8,000.00 | $40,000.00 | Construction |
| Supply and install three (3) 480-volt transformers | 3 | each | $12,000.00 | $36,000.00 | Construction |
| Supply and install metering equipment on final utility pole near dam | 1 | job | $7,000.00 | $7,000.00 | Construction |
| Connection from existing 480-volt, three-phase source to new service/distribution panel | 1 | job | $25,000.00 | $25,000.00 | Construction |
| Demolition and cutting of existing conduit and conductors | 1 | job | $10,000.00 | $10,000.00 | Construction |
| Disconnection of existing single-phase feed to the dam (contractor may salvage wire) | 1 | job | $5,000.00 | $5,000.00 | Construction |
| Coordination of easements with USACE and Lac qui Parle County | 1 | job | $8,000.00 | $8,000.00 | Professional Services |
| Coordination of metering, transformers, power access, and other needs with USACE and MN Valley Light and Power | 1 | job | $12,000.00 | $12,000.00 | Professional Services |
| Testing, grounding, submittals, and applicable state inspection for electrical upgrades | 1 | job | $20,000.00 | $20,000.00 | Construction |
| Potential for tree and brush removal | 1 | job | $15,000.00 | $15,000.00 | Construction |
| General labor, tools, equipment, and supervision for electrical upgrades | 1 | lot | $250,000.00 | $250,000.00 | Construction |
| Estimated Bid Value | $450,000.00 | ||||