| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Boiler Replacement (Building 7) | 1 | each | $150,000.00 | $150,000.00 | Construction |
| Boiler Replacement (Building 9) | 1 | each | $150,000.00 | $150,000.00 | Construction |
| Temporary Boiler Plant (Building 24) | 1 | each | $100,000.00 | $100,000.00 | Construction |
| East Parking Lot/Loading Dock Area Modifications | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| West Parking Lot/Access Modifications | 1 | lot | $50,000.00 | $50,000.00 | Construction |
| Estimated Bid Value | $500,000.00 | ||||
Sign up free to see the agency name, 5 documents, contact info, and the original bid posting link.