| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Restroom Demolition and Removal | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| ADA Compliant Toilet Installation | 4 | each | $1,500.00 | $6,000.00 | Construction |
| ADA Compliant Sink Installation | 4 | each | $1,200.00 | $4,800.00 | Construction |
| ADA Compliant Grab Bar Installation | 8 | each | $300.00 | $2,400.00 | Construction |
| ADA Compliant Mirror Installation | 4 | each | $400.00 | $1,600.00 | Construction |
| ADA Compliant Stall Installation | 4 | each | $3,000.00 | $12,000.00 | Construction |
| Restroom Flooring Installation (ADA Compliant) | 1 | lot | $8,000.00 | $8,000.00 | Construction |
| Restroom Wall Tile Installation | 1 | lot | $7,000.00 | $7,000.00 | Construction |
| Restroom Painting | 1 | lot | $3,000.00 | $3,000.00 | Construction |
| Plumbing Rework and Installation | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Electrical Rework and Installation (ADA Compliant Lighting) | 1 | lot | $12,000.00 | $12,000.00 | Construction |
| HVAC Modification (if required for ADA compliance) | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Permitting and Inspections | 1 | lot | $5,000.00 | $5,000.00 | Construction |
| Project Management and Supervision | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Contingency (10%) | 1 | lot | $14,180.00 | $14,180.00 | Construction |
| Estimated Bid Value | $150,000.00 | ||||