| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Site Preparation (clearing, grading, utility rough-ins) | 1 | lot | $250,000.00 | $250,000.00 | Construction |
| Multi-story Training Tower (concrete/steel construction) | 1 | each | $1,200,000.00 | $1,200,000.00 | Construction |
| Burn Building (fire-resistant construction, ventilation system) | 1 | each | $800,000.00 | $800,000.00 | Construction |
| Confined Space / Trench Rescue Prop | 1 | each | $150,000.00 | $150,000.00 | Construction |
| Vehicle Extrication Pad (concrete pad, drainage) | 1 | each | $75,000.00 | $75,000.00 | Construction |
| Classroom/Administrative Building (pre-engineered metal building or similar) | 1 | each | $400,000.00 | $400,000.00 | Construction |
| Paved Access Roads and Parking Areas | 1 | lot | $200,000.00 | $200,000.00 | Construction |
| Utility Connections (water, sewer, electricity, gas) | 1 | lot | $100,000.00 | $100,000.00 | Facilities |
| Security Fencing and Gates | 1 | lot | $50,000.00 | $50,000.00 | Security |
| Architectural and Engineering Services (design, permitting) | 1 | lot | $275,000.00 | $275,000.00 | Professional Services |
| Estimated Bid Value | $3,500,000.00 | ||||
Sign up free to see the agency name and the original bid posting link. Pro adds the 1 document, contracting-officer contacts and AI response outlines.