| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Flooring Replacement (Rooms 140 and 140A, Building 76) | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Electrical Modifications for X-ray Equipment (extending power conduits and cables, installing new power switches) | 1 | lot | $20,000.00 | $20,000.00 | Construction |
| Equipment Structural Support | 1 | lot | $7,500.00 | $7,500.00 | Construction |
| Project Management and Supervision (60-day project) | 1 | lot | $5,000.00 | $5,000.00 | Professional Services |
| Estimated Bid Value | $62,500.00 | ||||