| Item | Qty | Unit | Est. Unit Price | Est. Total | Category |
|---|---|---|---|---|---|
| Mobilization and Demobilization (Construction Equipment and Personnel) | 1 | lot | $25,000.00 | $25,000.00 | Construction |
| Erosion and Sediment Control Measures (Installation and Maintenance) | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Clearing and Grubbing (Vegetation Removal) | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Excavation and Grading (Stream Bank Reshaping) | 1 | lot | $75,000.00 | $75,000.00 | Construction |
| Riprap Installation (Bank Protection Stone) | 1000 | ton | $75.00 | $75,000.00 | Construction |
| Live Stake Installation (Bioengineering for Bank Stabilization) | 5000 | each | $5.00 | $25,000.00 | Construction |
| Coir Log Installation (Erosion Control and Vegetation Establishment) | 500 | linear foot | $20.00 | $10,000.00 | Construction |
| Native Vegetation Planting (Trees, Shrubs, Grasses) | 1 | lot | $30,000.00 | $30,000.00 | Construction |
| Seeding and Mulching (Temporary and Permanent Stabilization) | 1 | lot | $15,000.00 | $15,000.00 | Construction |
| Site Restoration and Cleanup | 1 | lot | $10,000.00 | $10,000.00 | Construction |
| Project Management and Supervision (On-site) | 1 | lot | $40,000.00 | $40,000.00 | Professional Services |
| Environmental Permitting and Compliance | 1 | lot | $20,000.00 | $20,000.00 | Professional Services |
| Estimated Bid Value | $350,000.00 | ||||